Atlas Road Markings Ltd 

'Avaliable for applying lines to your playground, parking bays, byways, motorways or runways'

Call or Email  Alan Fowler, Managing Director on 07809 894741 or 01442 865219  alan@atlaslines.co.uk 

 

  

       GENERAL METHOD STATEMENT

 

 

                                                                                       Method Statement No.Arm/13/02/07/A001

25 Pheasent close,

Berhamsted,

Herts.

HP42HQ,

 

 

Company Director:                                                                      A.Fowler

 

Signed:

 

Compiled By:

Arm Ltd Safety Advisor.                                                       G.Rooke (MCIOB)

 

Signed:                                                          

 

Date: 25th February 2008

 

 

KEY PERSONNEL

 

DESIGNATION

NAME

CONTACT No.

Logistics Manager

A.Fowler

01442865219

Contract Safety Manager

G.Rooke

07736595204

Out of Hours Emergency Contact

A.Fowler

07809894741

 

 

 

 

 

 

 

 

 

 

 

Method Statement.

 

 

Client                         - Frances Roah

Contract                    - LSC

Work Package         - White lining

 

           

Table of Contents

 

 

            1.0       Scope of Works                                                                   

 

            2.0       Labour force                                                                         

 

3.0             Tools & Plant

 

4.0       Working Methods

                                                                                                           

            5.0       Temporary Lighting and Power

 

6.0       P.P.E.                                                                                    

 

7.0      Risk Assessments

 

            8.0       Housekeeping and Storage                                                           

 

            9.0       Working Hours                                                                                             

      

         10.0       Particular Notes                                                                   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.0       Scope of Works     

          

                  Scope of Works

 

          The project includes the following elements: -

A 3 phase procedure involving the Demarcation of said areas within the project for the Road Line Markings as required within the given programme time in the contract supplied set by the main contractor.

 

 The operation for Phase1 is as Follows: -

The Issuing of areas ready to receive

 Paint Markings and Associated works.

 

·        This will be carried out within Health and Safety guide lines concerning Traffic and Pedestrian Management for the said works of line marking to take place at the above location.

 

·        Designated areas will be laid out for works to commence, and restricted access by others will be implemented until the said works are complete.

 

·        Areas to be marked out prior to painting by way of chalk line, canister Paint or emulsion paint to use as temporary guidelines.

 

·        Line marking /Spraying equipment information to be included within the COSSH data if requested by contractor.

 

·         On completion of said areas all dust /debris and excess materials will be taken and disposed of according to the main contractor environmental requirements and the end of each working day.

 

Phase 2.

 

·        The same principles will be undertaken by way of isolating areas due for painting, to segregate those unauthorised to the area, until the area is dry and safe to walk or receive the movement of Traffic

 

·        All works are to be carried out by ARM operatives adhering to the correct PPE requirements set out by the main contractor and within the task specific Risk Assessment, throughout the duration of the works

 

·        This method of operation is to be carried out throughout the duration until all works are complete and all associated materials and debris to be cleared and all main contractors H&S requirements have been met.

 

 

 

Phase 3.

 

 On completion of phase2,

A sign Off procedure will be required following an inspection of all works asto allow occupation of finish areas to the main contractor / Client.

 

 For full scope works refer to drawings issued by main contractor.

 

 

2.0      Labour Force

 

Site Manager – A. Fowler.

 

Installation - Team ( Comprising of up to  6 operatives T.b.c)

 

3.0      Tools & Plant

 

Airless sprayer

General prepping Hand Tools

 

 

Powertools  -

Petrol Grinders & Scabblers

Air ? vacuum tools for dust extraction

 Extension Leads110v only

 

            Any power tools required will be 110 volt.

            All operatives handling plant will have received the appropriate                         training.

 

 

N.B.    EAR AND EYE PROTECTION WILL BE PROVIDED AND

WORN WITH THESE TOOLS.

 

 

 

 

 

 

 

 

 

 

 

 

4.0       Working Methods

 

            Materials Delivery

 

                           

§           Initial deliveries of skips will be made to site under the control of

The site security or main Contractors site manager.  These will be booked and stored only by arrangement with Arm Ltd Management.

 

                   Subsequent site deliveries will comply with the following -

         

§            Arm Ltd to book times for deliveries and forklifts in advance,

       Following the allocation of a temporary storage area.

§           Bookings to be agreed with Site Manager and confirmed in writing

§           All bookings to be scheduled on suitable forms.

§           Information issued to Loading Bay supervisor and Security each afternoon

       For the following days work.

§           Materials storage on site will be limited to designated areas and only on a

                   Short term basis.

 

 

Waste Removal –

 

       Arm Ltd Waste removal team to ensure -

                                     

·        Emptying and clearing all waste to designated

Areas.

·         To leave waste or spoil in agreed locations prior to removal from site.

 

General Works

 

·        Safety measures for power tools must be strictly adhered to.

·        Areas during demolition should be designated via clear walkways and working areas, or closed off completely for Health and Safety.

·        All waste and debris will be cleared regularly.

 

 

 

ALL OPERATIVES MUST WEAR APPROPRIATE

PPE AT ALL TIMES

 

 

 

 

 

 

 

 

5.0       Temporary Lighting and Power

 

            All 110v as supplied within contract.

            Main Contractor to supply lighting if required.

           Petrol fuel for tools is to be brought to site on a daily basis and remove from                                     site at the end of every working day.

 

6.0       P.P.E.

 

The equipment to be worn by all the company's operatives on site will

Consist of: -

 

                        (i)         Hard Hats

                        (ii)        Safety Footwear (boots with toe protection)

                        (iii)       High Visibility Jackets

                        (iv)      Suitable Robust clothing

 

            Any additional requirements for PPE identified in Risk                           Assessments to include but not limited to: -

 

                        (i)         Gloves

                        (ii)        Face Masks or respirators

                        (iii)       Goggles

(iv)              Ear Protection

 

 

7.0       Risk Assessment  

 

            Operation/Process  -         Delivery management

 

            Hazard                                                          Risk

           

            Manoeuvring vehicles                                   Medium

 

            Persons at Risk

 

           Arm Ltd operatives

            Trade Contractors                                  Low / Medium

            Main Contractors

            Public

 

           

 

 

 

Control Measures

           

            Manager specifically dedicated to task.

            Experienced, trained operatives to be used

            Correct PPE to be worn including Hi-Viz. jackets

            Scheduled vehicles are only to be allowed site access.

Vehicles to operate under hazard - warning lights. All areas under demarcation to be adequately shut off and clearly visible signage posted prior to commencement.

 

 

7.1       Risk Assessment  - 

 

            Operation/Process  -         General Works– Use of Power Tools

                                                                        (Where required)

            Hazard                                              Risk

           

            Electric shock,                                 (Low)          110v power only.

            Physical Injury,                                       All safety measures in place.

           Working at height                            Demarcation Areas to be Zoned Off

                                                                           Prior to commencement

 

 

            Persons at Risks

 

            Arm Ltd Operatives

            Main Contractor’s Representatives                        Low / Medium

            Other Trade Contractors

            General Public

 

 

            Control measures

           

            Operative to have received appropriate training

            PPE to be worn, including gloves, eye and hearing protection.

            All power tools to be 110v

Ensure cable routes do not form trip hazards or allow cables to be damage

 

 

All operatives handling plant will have received the appropriate training.

 

           

 

 

 

 

 

 

Power Tools Generally

 

The following rules apply to all items, whether supplied by the Company or outside suppliers:

 

            a)         All power tools must be thoroughly inspected before use and at                                    regular intervals thereafter.

            b)         Faulty tools must never be used.

            c)         Under no circumstances should tools be left out on site.

            d)         Tools must be stored in a clean dry store.

            e)         Ensure that the correct tool is being used for any particular                                            operation.

f)          The operator must ensure that the tools are maintained in a                                           satisfactory condition and must notify the Supervisor of any                                            defects.

 

            N.B.    EAR AND EYE PROTECTION WILL BE PROVIDED AND                                                                WORN WITH THESE TOOLS.

   

7.2       Risk Assessment 

 

Operation/Process  - General Demo

                                        Waste Removal

                                                                                   

            Hazard                                  Risk

           

            Exposure or contact with                  Low          Damping down and masks

Harmful substances; -

 

 Dust,                                              Low            Safety Masks to be worn .

 Dust / Small Debris                    medium        Safety measures in place.

 

Moving Plant                               medium         Banks man in attendance        

 

            Persons at Risk

 

           Arm Ltd  Operatives

            Other Trade Contractors              Medium

            Clients Representatives

           

           

 

 

 

 

 

 

 

 

Control measures

 

Damping down with hosepipe may be required to reduce the amount of dust that may be exuded due the preparation prior to painting.

Main Contractor to ensure that there is an adequate water supply throughout duration of works required.

 

           

·        Suitable signage to be displayed to warn of works.

·        All Operatives to wear appropriate PPE to include dust masks or respirators.

 

Area to be kept well ventilated to avoid the build-up of dust in moderately confined areas.

 

 

8.0       Housekeeping and Storage

 

All waste material and debris to be cleared by ArmLtd operatives to skips provided on a regular basis.

 

Materials will be neatly stored adjacent to the works where applicable. Site manager to designate all locations within the site boundary.